We just received our signage and I have built my main project the will run 24/7. The question is there a way I can add other projects onto existing ones? Here is what I'm trying to do without building one for each day of the week and having them expiring. I have my main project running and I want to run food offers on certain days of the week and have them drop off at the end of the day. I just don't want to build these schedules 7 more times to my end result.
1 comment
-
Brandon Hi Tony,
In the Publish tab, the schedule can include more than one presentation and presentations can be set to repeat, so if Monday and Tuesday use the same presentation, you can set up the schedule for that presentation to repeat weekly Monday and Tuesday.
If you're using Local File Networking, you can also have a "regular" schedule and set an interrupt schedule that overrides the regular schedule as necessary.
See page 99-102 of the BrightAuthor 3.8 User Guide (or relevant Publishing section in the user guides for newer versions)Alternatively, you can have one presentation branch to another presentation by using Switch Presentations
http://support.brightsign.biz/entries/21121606-How-do-I-switch-presentations-or-change-layouts-in-BrightAuthor-