0

Scheduling

Hello,

Had a quick question about scheduling for presentations.

We have several HD1022 players that we have been using for a while and have recently created a bright wall  for the 8 players to sync video. However now it seems i am unable to schedule this presentation with an earlier presentation we made to turn on/off the players via an rs232 command.

Is there anyway to schedule a classic presentation with a bright wall presentation? for example, i'd like to first turn on my projectors(a regular presentation), and then move from there to showing my bright wall .

If there is not, is there another way to synchronize video playback like the bright wall does?

2 comments

  • 0
    Avatar
    ^UD\_$

    We have never mixed BrightWalls and traditional presentations.

    For simplicity, you want to opt for a single traditional presentation that does everything that you need.

    You can use the Synchronize event, along with enabling the enhanced synchronization feature under:

    Presentation Properties -> Interactive

    Sending a UDP command from a master to all of the players in the video wall, can also do the job.

    I hope that helped.

  • 0
    Avatar
    Brandon

    You can't mix BrightWall and standard Presentations in the same schedule.

    So as Udi recommended, you should use Synchronized standard presentations which can do the same thing as BrightWall, plus handle your additional interactivity.